Valley Line West LRT: Stony Plain Road and 149 Street intersection reopens
The intersection of Stony Plain Road and 149 Street reopened to traffic on October 7, approximately one week ahead of schedule. This intersection was partially closed to vehicle traffic on August 15, as part of the Valley Line West accelerated roadwork plan.
The intersection of 95 Avenue and 156 Street also reopened to traffic on October 3.
Accelerated roadwork continues along 104 Avenue between 105 Street and 121 Street. The work has reduced 104 Avenue to one lane eastbound and one lane westbound. This work is anticipated to continue for the remainder of the construction season.
The three-phased accelerated roadwork plan began in April with the goal of getting the majority of the roads along the Valley Line West alignment into their final configuration by the end of 2025. These are the final two of eight major intersections that were partially or completely closed this summer to complete the road and track installation as quickly as possible. All intersection work was completed on or ahead of schedule.
The City and Marigold Infrastructure Partners (MIP) recognize this work is disruptive to commuters, residents and businesses, and we appreciate everyone’s continued patience.
Valley Line West construction is anticipated to be complete in 2028, followed by an extensive testing and commissioning phase to ensure safety and reliability before the line opens.